Denver Zoo Elephant Exhibit First in Nation to Earn LEED Platinum

Text size: A A
[ Page 1 of 2 ]

 

Photo courtesy of Kiewit
The state-of-the-art animal exhibit utilizes a first-of-its-kind gasification plant.
Photo courtesy of Kiewit
The project redeveloped approximately 10 acres of existing zoo exhibits and service areas on the south side of the zoo campus.
----- Advertising -----

2012 Judges Special Recognition


2012 Best Project

Sports/Entertainment Category

Toyota Elephant Passage at Denver Zoo

Denver

The Toyota Elephant Passage Exhibit at the Denver Zoo is the first exhibit of its kind in the country, setting an example in sustainability for other zoos to follow. Many other zoos have LEED-certified buildings; however, the Toyota Elephant Passage (TEP) is the first LEED-Platinum-certified zoo exhibit in the U.S.

The zoo intends to turn more than 90% of the waste it produces into gases that can be harnessed for energy. The state-of-the-art TEP exhibit utilizes a first-of-its-kind gasification plant that is expected to supply more than 10% of the zoo's total power needs. The plant generates its power from animal waste and garbage collected at the zoo.

Kiewit provided preconstruction and construction services for the new exhibit. The project redeveloped approximately 10 acres of existing exhibits and service areas on the south side of the zoo campus. Kiewit's scope of work included the planning and construction of animal exhibits and their overnight quarters, support and ancillary facilities, and utility relocations and site improvements.

The existing site within the Denver campus was cleared, including demolition of approximately 17 existing structures. To minimize the environmental impact, 58 trees were protected during demolition and construction, and 30 trees were relocated within the project boundaries or elsewhere on the campus.

Communication and collaboration among all team members were critical at each step of the project. For instance, because elephants can sense water up to 5 ft underground, Kiewit had to bury the water lines below 5 ft to prevent them from being dug up. Several miles of underground piping were laid throughout the exhibit, and potential hazards at every linear foot had to be considered to ensure the lines couldn't be damaged.

The entire project team was extremely considerate of the animals. Everything from vehicle backup alarms to ordinary dust kicked up from construction operations was taken into account to ensure that animals were not disturbed or troubled in any way during construction.

Key Players

Owner: City and County of Denver, Denver Zoological Foundation, Denver

Architect: CLR Design Inc., Philadelphia

General Contractor: Kiewit Building Group Inc., Englewood, Colo.

Civil Engineer: SEH, Denver

Structural Engineer: Monroe & Newell, Denver

MEP: The RMH Group Inc., Lakewood, Colo.

Keywords:

[ Page 1 of 2 ]
----- Advertising -----
Reader Photos
Photos from ENR Mountain States Photo Showcase
Dodge Lead Center
Search for local construction projects OR CALL 877-234-4246 and get a FREE Lead Now!
Search by Project Type & State





----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.