First Section of Ambitious Mountain View Corridor Opens to the Public

Text size: A A

The parallel, three-mile stretches of frontage road crossing what used to be farmland west of the Utah County city of Lehi might seem simple enough, but they are the key first portions of the Mountain View Corridor to open for public use. The project is an ambitious 35-mile freeway, transit and trail system connecting 13 municipalities along the western edge of the Salt Lake Valley.

Courtesy of UDOT
This is one of two bridges over the Jordan River that are part of the recently completed first portion of the Mountain View Corridor highway project in Salt Lake Valley, Utah.
----- Advertising -----

The $120-million project, known locally as 2100 North, includes design, right-of-way acquisition and construction of the roads, two railroad overpasses, two bridges over the Jordan River and improvements to the river’s trail system.

The one-way, two-lane roads, one eastbound and one westbound, connect Interstate 15 at Lehi on the east to Redwood Road, a major north-south highway on the western end of the Salt Lake Valley. The space between the roads will eventually become a freeway when the Mountain View Corridor project is built-out over the next 10-15 years, according to the Utah Dept. of Transportation.

“This is a significant milestone to open the first section of the Mountain View Corridor in the community,” says UDOT Project Director Teri Newell. “As communities expand in Northwest Utah County, the need for a transportation system to support the growing population is crucial.”

Ed Rock of New York-based Parsons Brinckerhoff says the company has been working with UDOT on the overall design of the Mountain View Corridor since 2003. He says the goal for this first section was to stay within budget and design in anticipation of future build-out. “The money for the freeway was not available now nor is a freeway needed at this point,” says Rock. “We designed this section to preserve right-of-way for the freeway and to add capacity for now and to have interchanges for the freeway in the future.”

The design team also worked with the Utah Transit Authority in constructing an overpass for the commuter rail line to Utah County, currently under construction. The commuter rail lines run parallel to active Union Pacific lines so they also required an overpass.  

“To save future costs and disruptions, we included the Union Pacific and UTA bridges in this project,” Rock says. “We left the existing UP track in place and built the commuter rail bridge. Then, since there is not an active commuter rail line yet, the UP traffic could be put onto that without having to do expensive shooflys while we got the UP bridge rebuilt.”

Rock says building on the site, which was primarily agricultural land and former river bottom, posed a few challenges. “We had to minimize impacts to the wetlands and stabilize the soils right up to the river,” he says.
Kendall Page, project manager and chief estimator for the project’s general contractor Hadco Inc. of Lehi says just over a million tons of surcharge fill was hauled into the site.

“We had some areas that settled almost twice as much as we expected,” says Page. “That delayed us some, but we were able to work in other areas while we waited for the surcharge to settle.”

Keywords:

----- Advertising -----
Reader Photos
Photos from ENR Mountain States Photo Showcase
Dodge Lead Center
Search for local construction projects OR CALL 877-234-4246 and get a FREE Lead Now!
Search by Project Type & State





----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.